Dockwater Open Season Pricing
In connection with Dockwater’s recently announced Open Season, we are pleased to offer the below pricing to all customers in our covered service territory.
If you are a consumer of process water or demineralized water in our service territory, please reach out to information@dockwater.be.
Service Territory (Process Water)
Notional Rate €/m3
Effective Rate1€/m3
Minimum Average Water Demand
Right Bank
0.79
0.59
>1,000 m3/h aggregate
Kallo
0.87
0.65
>1,000 m3/h aggregate;
>350 m3/h Kallo
South Bank
0.87
0.65
>1,000 m3/h aggregate;
>800 m3/h South Bank
Volume Discount
Approx. 0.10 reduction for all customers at all service locations
>2,500 m3/h subscription
1 Effective Rate as estimated from reduced make-up water requirements, less frequent blow downs, and lower chemical consumption in cooling tower processes; analysis available upon request.

MOU Summary
Purpose: Non-binding MOU where the Parties agree to cooperate and negotiate in good faith to enter into a Water Purchase Agreement (WPA) based on the proposed Project development schedule
Project Capacity: 1,000 to 3,100 m3/h desalination facility and distribution pipeline
WPA Main Terms
- Volumes based on Customer average annual demand
- Water Tariff to have a fixed (take-or-pay) component and a variable component both subject to indexation (greater of 1.75% or to-be-agreed CPI). The fixed component is intended to cover capital cost and fixed O&M costs. The variable costs to be a passthrough to Customer at certain committed efficiency levels (electricity; water intake fee; chemicals)
- Customer to have the ability to increase/ decrease water volumes due to seasonality and increased/ decrease demand, subject to certain limits, every operating year
- Water Tariff based on final plant capacity and location of the Customer (see Pricing Sheet)
- Multiple levels of reliability based on back up options available described in Back Up strategies page
- Tenor of the WPA to be not less than 18 years from the Project Commercial Operations Date (“COD”)
Termination
- Substitution of MOU by the WPA
- Such earlier date as the Parties mutually agree
- If after 24 months Dockwater has not started the construction of the Project
High Level of Reliability and Multiple Levels of Back Up
Multi-layered redundancy ensures extremely certain water supply
Plant Outage Back Up
Plant is designed to be 100% reliable
- Availability guarantee under the Suez O&M contract in excess of 99.5%. Suez proven historical availability in other similar desalination plants is 100%.
- Greater than 20% redundant stand-by capacity installed across all processes (plus stored inventory on-site spare filtration units and pumps)
- UF 23%, SWRO 23%, BWRO 25%; EDI 25% redundant capacity and spare pumps and other equipment in each process area
- Over-dimensioning of duty pumps and filters; can run at higher pressure and increased flow to cover for unplanned downtime in excess of 20% of capacity
On site process water storage for two consecutive days of full plant capacity
- Any contamination in dock water should be solved in 48 hours (problem floats or sinks)
Water Supply Back Up
- Alternative Water Supply Insurance: Dockwater will pay the customer the cost difference between the price customer will pay for back up drinking water from the utility and the price the Project charges customers for its process water under the WPA (up to 1.0 EUR/m3 ). The utility has an obligation to provide back up.
- Wastewater Recycling: During Project development, Dockwater plans to secure treated wastewater (availability has been confirmed) as an additional water source that can be treated to process water at the desalination Plant providing full circularity in line with the Blue Deal.
Open Season and Project Schedule
Activity
Parties
Date
Open Season Announcement
Project Company
25 October 2021
Form of MOU Issued to Customers
Project Company
25 October 2021
Customer Roundtable
Current and Potential Customers
First week of December 2021
Execution of MOU
Both Parties
31 January 2022
Water Purchase Agreement
("WPA") Draft Issued
Project Company
15 February 2022
Permits Filed
Project Company
15 March 2022
WPA Agreed
Both Parties
30 April 2022
Commencement of Construction
Project Company
31 December 2022
Commercial Operations Date
Project Company
30 September 2024